Engines & Gearboxes

Diesel and dual-fuel engines, generator sets and reduction gearboxes for main propulsion and auxiliary power.

Test-bed load steps and fuel consumption1Alarm and shutdown function tests2Gear tooth contact and oil cleanliness3Coupling and flexible mount verification4Scope of supply, spares and preservation5
Illustrative process visualization

Engines and gearboxes are normally produced by established makers and tested on a test bed. The buyer's interest is that the shop test follows the agreed programme, protection devices are proven, and the scope of supply is complete with the correct documentation and emission certificates.

Inspection checkpoints

The numbers correspond to the checkpoints marked in the diagram above. Select a point in the diagram to jump to its explanation.

  1. Test-bed load steps and fuel consumptionThe engine is run through the agreed load steps, typically 25, 50, 75, 100 and 110 percent. Fuel consumption, temperatures and pressures are recorded at steady state and compared with the maker's guaranteed values.
  2. Alarm and shutdown function testsEach alarm and shutdown is triggered on purpose: overspeed, low lubricating oil pressure, high cooling water temperature and the others listed in the specification. The set points and the reaction of the safety system are recorded.
  3. Gear tooth contact and oil cleanlinessTooth contact is checked after the test run, when the pattern shows the real load distribution. Oil samples and filter inspection confirm that no manufacturing debris remains in the lubrication system.
  4. Coupling and flexible mount verificationCoupling type, size and bolt tightening are compared with the torsional vibration calculation, because a different coupling changes the vibration behaviour of the whole shaft line. Mount hardness and height are checked against the installation drawing.
  5. Scope of supply, spares and preservationThe delivery is counted against the order: loose parts, tools, spare parts and documents. Openings are sealed and machined surfaces and the interior are preserved for the expected storage period at the yard.

Typical documentation

Shop test report, EIAPP or equivalent emission documents, class certificate, parts list, installation and operating manuals.

Related inspection and engineering services