Factory acceptance test
The FAT takes place at the manufacturer. It proves that the equipment, on its own, meets the specification: rated performance, protection functions, workmanship and documentation. Problems found here are corrected with the maker's tools, people and spare parts at hand. The limit of a FAT is that ship interfaces are simulated.
Harbour acceptance test
The HAT takes place with the vessel alongside the outfitting quay. It proves installation: foundations, piping, cabling, interfaces and basic function. A thorough HAT keeps sea trial time for what can only be shown at sea.
Sea acceptance test
The SAT is the part of sea trials dedicated to a system. It proves performance under real load and motion: propulsion power, steering, manoeuvring, navigation sensors and automation. Results are compared with contract guarantees.
Where a buyer's representative adds value
Reviewing the procedure before the test, checking instrument calibration, recording data independently and agreeing the punch list before leaving. Deficiencies should be written, owned and dated.