FAT, HAT and SAT: three acceptance stages and what each one proves

Marine equipment is accepted in steps. Understanding what each step can and cannot prove helps buyers decide where to attend.

Factory acceptance test

The FAT takes place at the manufacturer. It proves that the equipment, on its own, meets the specification: rated performance, protection functions, workmanship and documentation. Problems found here are corrected with the maker's tools, people and spare parts at hand. The limit of a FAT is that ship interfaces are simulated.

Harbour acceptance test

The HAT takes place with the vessel alongside the outfitting quay. It proves installation: foundations, piping, cabling, interfaces and basic function. A thorough HAT keeps sea trial time for what can only be shown at sea.

Sea acceptance test

The SAT is the part of sea trials dedicated to a system. It proves performance under real load and motion: propulsion power, steering, manoeuvring, navigation sensors and automation. Results are compared with contract guarantees.

Where a buyer's representative adds value

Reviewing the procedure before the test, checking instrument calibration, recording data independently and agreeing the punch list before leaving. Deficiencies should be written, owned and dated.