Marine Automation & Control Systems
Alarm and monitoring, power management, propulsion control and integrated automation systems.
Automation ties the vessel's systems together and is frequently the last system to be ready. Structured testing against the I/O list and cause-and-effect matrix, at FAT and again on board, prevents long commissioning delays.
Inspection checkpoints
The numbers correspond to the checkpoints marked in the diagram above. Select a point in the diagram to jump to its explanation.
- Operator stations and mimic displaysMimic pages are compared with the P&IDs and the functional specification. Alarm lists, colours, units and access levels are checked for consistency across all operator stations.
- I/O list and loop checksEvery input and output is exercised from the field side or a simulator and observed at the operator station. The I/O list is signed line by line so that no channel is left untested.
- Communication links and redundancyNetwork cables are disconnected and controllers switched off one at a time to prove that redundant links and processors take over without loss of control or false alarms.
- Sensors and field devicesField devices are checked for the correct range, material and certificate, mounting position, cable entry and protection class for the location on board.
- Cause-and-effect and failure-mode testsEach cause in the matrix is initiated and the effects are observed: alarms, shutdowns, start of standby units. Failure modes such as loss of power or signal are tested for safe reaction.
Typical documentation
Functional design specification, I/O list, cause-and-effect matrix, FAT and commissioning records, software version record.