Choose points by risk
Put hold points where a later operation will hide or lock in the result: before welding a closed section, before coating, before closing a casing, before packing. Use witness points for tests whose records can be reviewed if attendance is missed.
State the criterion, not only the activity
Each ITP line needs a reference document and an acceptance criterion. A line that says only that an inspection takes place gives the inspector nothing to accept or reject against.
Agree notification
A hold point only works if the supplier must notify in time and may not proceed without release. Notification periods belong in the purchase order.
Close the loop
Signed ITP stages, with the records they refer to, become the backbone of the manufacturing record book delivered with the equipment.